Parking lot
The parking lot is prepped and ready for curbs. The 3rd building is nearing completion and the last building will be ready soon for insulation.
Friday, August 15, 2014
Friday, August 8, 2014
Update
A majority of the sod has been placed on building B - should be wrapped up on Monday.
Building C - the elevator has arrived and installation will begin shortly. A majority of the exterior is complete and should be wrapping up in a couple weeks. Preparation has begun for sidewalks and asphalt. The 3rd floor is nearly finished. 2nd floor most of the finish carpentry is complete. We will be painting out the first floor next week.