Wednesday, July 30, 2014

Update

Building C - 3rd floor cabinets are being installed. 

2nd floor is being primed today and painted Friday. 

1st floor is drywalled and being taped. 

Building D - most of the roof is sheathed and will be dried in early next week. 






Friday, July 18, 2014

Revere Landscaping

The sod has been places around building A and the Clubhouse.
We will place the sod around building B early next week.