Building A is nearly complete - with just a few more pieces of siding to go - the interior is complete and the building is occupied.
The club house is wrapping up. We have a little more flooring and finish carpentry work to complete the interior.
The pool is dug - we will pour the deck early spring and get the pool up and running around May 15th.
Building B - the soffit and fascia is nearly complete and the masonry begins Wednesday. The 3rd floor will be ready to insulate mid week.