Friday, August 30, 2013

Revere Update

The roof trusses are on building A, 
we will have a majority of the roof sheeted and start roofing by the 5th





The clubhouse is shingled, windows going in and starting rough mechanicals.


Friday, August 23, 2013

Revere Apartments - Update

Revere Building A - all 3rd floor walls are set and ready for roof trusses Monday.


Clubhouse - roof is sheeted and ready for shingles Monday.


Revere Building B - finishing up the last of the foundation and 
preparing for precast middle of next week.



Wednesday, August 7, 2013

Building A, B, and the Clubhouse


Building B: 1/3 of the foundation is poured and the next third have forms set for another pour.




Building B



The Clubhouse: all the walls are built and roof trusses 
were delivered today.

A look out the windows of the community room.


Another view out of the community room - this time facing the pool.


Building A - 3rd floor, floor trusses have been set - next week we will 
start building 3rd floor walls.