The Revere Apartments
Tuesday, July 23, 2013
Building B
A majority of the footings are poured for building B and we
will begin setting the foundation forms soon.
Clubhouse
The clubhouse exterior walls are starting to go up.
Building A
2nd floor exterior walls are going up and retaining walls are going in.
Thursday, July 18, 2013
Building A & Clubhouse
All of the 1st floor interior walls are complete and we are putting the 2nd floor deck on. The elevator shaft is up through the 3rd floor.
The floor of the clubhouse is nearly finished and we will begin framing wall on Monday.