Friday, June 28, 2013

Building A

All of the 1st floor exterior walls are set. 
Working on the faming of party walls and the corridor. 




Sunday, June 16, 2013

Building A & Clubhouse

The pre-cast is all set and grouted and ready for 1st floor walls to be built.


The clubhouse is backfilled and ready for underground plumbing and electric.


Sunday, June 9, 2013

Building A and Clubhouse


The foundation for building A is complete and Monday we will start placing the pre-cast. The clubhouse foundation is also finished and on Tuesday we will start backfilling the interior and exterior and should be ready for underground plumbing and electric on Thursday.