Tuesday, November 4, 2014

Update

The last building at Revere opened Friday, October 31st. All landscape trees and shrubs are planted. The sod is starting to go in as we wrap up the irrigation.


Friday, October 24, 2014

Thursday, October 23, 2014

Revere D

The 3rd floor and most of 2nd floor is comete. 1st floor will be wrapped up early next week. Final inspections for Revere D will begin on Monday. 

The landscaping is also starting to go in. 



The final layer of the parking lot is complete. 




Monday, October 6, 2014

Update

Building C - landscaping is in and putting in final preparations for sod tomorrow. 

Building D - 3rd floor cabinets are complete and countertops are going in. Carpet pad is being installed too. 






Tuesday, September 30, 2014

Building D

The 3rd floor - cabinets are going in and most of the light fixtures are installed. 



2nd floor is primed. Will be painted out by Thursday and cabinets will start going in Monday. 


1st floor - all but 2 units and the corridor are drywalled. 






Sunday, September 7, 2014

Building D

The 3rd floor insulation will be complete Monday. We have already started running resilient channel on the ceiling and hanging drywall.